Mihan-SEZ is under construction right now. Just to update those who hail from Nagpur or central india -

- Flyover joining wardha road to Mihan SEZ is almost complete now
- Outer Ring road (1/4 from Amaravati Road to Wardha Road) is complete (excluding major bridge work)
- Outer ring road from wardha road joining to North near Kamthi work has started (this is actually part of North-South Corridor)
- Administrative building is complete and operational

this site lists latest information about Mihan project with few photographs -