  • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

    As per practice, builders start registration once 20% payment is made and plinth of building has come up.
    If even after few slabs builder is not registering then needs investigation.

    Comment


    • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

      In today's Property Times paper they have advertised new Rent scheme wherein they promise to pay every month Rs 25K as rent till possession is given.
      Is this applicable to existing buyers as well ?
      If not then u must fight for the discrimination ..

      Comment


      • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

        Quick Question

        By any chance were the payments made in the name of Acme Property Developers Pvt. Ltd?

        Curious as, there is a project in Chembur under the name of Veena Serenity where the cheque needs to be issued in the name of Acme Property Developers Pvt. Ltd.

        Want to ensure there is no link with the same Acme group.
        Last edited by mantrig; November 17 2014, 11:37 AM. Reason: Name of the developer edited

        Comment


        • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

          Information related to EC

          Dear All Buyers,

          Please read MOM for 75th SEIAA

          It seems now after 28th Oct Acme Oasis got EC clerance

          dont know about other cleranaces and construction status...

          Please buyers in Mumbai shall check and update all of us..
          https://ec.maharashtra.gov.in/ SEIAA select MOM 75th Refer item no. 20

          Comment


          • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

            khekda....i agree but what we have with us
            Any body have registration done in this project... ideally there is no official document till date

            Comment


            • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

              That is TRUE... perhaps the Vasant oasis buyers must been registered. We don't have any document except for the allotment letter and the demand letters.

              Anybody here who have been registered !!

              Comment


              • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

                Anybody there in Mumabi please visit the site this week end
                Talk to representative about EC & other CC

                Then update to all of us

                Comment


                • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

                  Anyone received demand letter for Tower 2 - 5th slab completion?

                  Comment


                  • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

                    Hi,
                    I am received the payment notice for the completion of 5th Floor in Tower 2.

                    Comment


                    • Re : Acme Oasis, Acme Group, Kandivali East, Mumbai

                      I when to the site, currently the Floor 6 is in Progress, and the next payment might come in January 1st Week.
                      Currently they have CC till upto 11 Floor for Tower 2 i.e 3 Podium + 8 Floor

                      Comment