  • Re : Crossing Republik Latest Updates & Reviews

    Originally posted by hindustan View Post
    Actually we should accept the facts that every area have Pro and Cons. Everyone wants to only listen about positives about his builder, area but no one want to hear negatives. If we ask builder to give status about delay in construction, he replied simply ki sirji rate bar gaye hai aap tension kyu le rahe ho. Similarly if any of our friend in circle ask status about our flat which is under dispute we try to hide the facts by saying rates are appreciating, so no tension. Hamare rate to 300% bar gaye hai paper par. So it is not only investors who promote areas even we end users try to promote our project among our friend circle even if we are not happy with builder or area. This will trap more end users who will then do the same.
    So this will help no one except those faulty builders who are making big revenue even they delivered shitty projects.
    So who should be blame, we end users who trap others by giving false picture or we keep on blaming brokers, builders every time??
    I agree with @hindustan...... People get emotionally attached to their investments, which sometimes create false perception rather than reality......but it's somewhat natural on this earth.."Har Maa koh apna baccha pyara hota hai" .....

    Another perspective to it is now people have become mature they know there is lifecycle of project and no project (barring exceptions) is delivered in 2-3 years time as promised by builder ...it take good 5-6 years to become really liveable .. so they just chill and enjoy the talks.....

    Comment


    • Re : Crossing Republik Latest Updates & Reviews

      Originally posted by gandabaccha View Post
      CR wale bhaiyo,

      Bura mat manana , but did somebody tried to enter/exit CR in morning 8am to 10 am .
      Some one told me it takes 30 min to go out of CR in morning becoz of narrow roads.

      once CR will be full of residents what will be the condition ..

      Just imagine guys.
      Nor in support nor against:

      I am working in Noida and few of my friends are commuting daily from CR, and they are quite happy..... never heard anything like this from them.

      Comment


      • Re : Crossing Republik Latest Updates & Reviews

        posting on behalf of our group very active at township level (CROMA)


        Update on Widening of Shaberi Pulia, Control Jam on Shaberi Pulia and Connectivity Improvement for Noida via Noida Ext.

        Dear Residents of Crossings Republik,

        Looking into the critical subject issue on priority , once again CROMA Executive team had a detailed discussion with management team Crossings Infrastructure Pvt. Ltd. ( hereinafter referred as CIPL) on Saturday i.e. 1.09.2012. After a detailed discussion on many points from the charter of demands update on critical point of Shaberi Pulia and connectivity to Noida, the following response in point wise as under:
        · 6 Mtr pulia design is passed for construction. CIPL has limited role now except to pay for its construction only.Construction will be done by U.P.Irrigation Department and expense will be bear by CIPL management

        · Tentatively Construction will be start by Oct’12

        · Divider on road, message of one way near temple and on shaberi side will be placed soon to educate traffic. One way traffic should be followed by residents as per timings i.e. Morning -8.00.- 10.30 A.M, Evening : 5 - 8.00 P.M.

        · Connectivity with Gaur city via Crossings Republik from road behind GH-07 society can be expected to get resolved in a year as its require lot of paper work and follow up work from different authorities due to land ownership issue.

        It is a request to all the residents that while using the route from Crossings Republik towards Noida Extension and vice-versa, please follow single lane to avoid jam in peak hrs. Please bear in mind that no one else will come, its we who all have to make the system in place to make our life better.

        Hope the above information clear a bit of picture on the subject. We will timely update the status as per our our meetings with CIPL management.

        CROMA always stands for better infrastructure development at Crossings Republik with your valuable suggestions.

        Best Regards

        Akhil P.Chhabra
        General Secretary-CROMA
        Crossings Republik Flats Owners Association (Regd.)

        Comment


        • Re : Crossing Republik Latest Updates & Reviews

          for any updates on township related thing please visit Crossings Republik Resident Welfare Association - CR RWA

          recently we contributed to the CROMA fund for fighting the DG issue so that it can rest in peace for always:-

          Please note:- The High Court has given judgement in favour of ownership pf land to GNN not to build DG yet.. but anyway its a long legal fight and we are on it

          Comment


          • Re : Crossing Republik Latest Updates & Reviews

            Originally posted by nilabh9 View Post
            posting on behalf of our group very active at township level (CROMA)


            Update on Widening of Shaberi Pulia, Control Jam on Shaberi Pulia and Connectivity Improvement for Noida via Noida Ext.

            Dear Residents of Crossings Republik,

            Looking into the critical subject issue on priority , once again CROMA Executive team had a detailed discussion with management team Crossings Infrastructure Pvt. Ltd. ( hereinafter referred as CIPL) on Saturday i.e. 1.09.2012. After a detailed discussion on many points from the charter of demands update on critical point of Shaberi Pulia and connectivity to Noida, the following response in point wise as under:
            · 6 Mtr pulia design is passed for construction. CIPL has limited role now except to pay for its construction only.Construction will be done by U.P.Irrigation Department and expense will be bear by CIPL management

            · Tentatively Construction will be start by Oct’12

            · Divider on road, message of one way near temple and on shaberi side will be placed soon to educate traffic. One way traffic should be followed by residents as per timings i.e. Morning -8.00.- 10.30 A.M, Evening : 5 - 8.00 P.M.

            · Connectivity with Gaur city via Crossings Republik from road behind GH-07 society can be expected to get resolved in a year as its require lot of paper work and follow up work from different authorities due to land ownership issue.

            It is a request to all the residents that while using the route from Crossings Republik towards Noida Extension and vice-versa, please follow single lane to avoid jam in peak hrs. Please bear in mind that no one else will come, its we who all have to make the system in place to make our life better.

            Hope the above information clear a bit of picture on the subject. We will timely update the status as per our our meetings with CIPL management.

            CROMA always stands for better infrastructure development at Crossings Republik with your valuable suggestions.

            Best Regards

            Akhil P.Chhabra
            General Secretary-CROMA
            Crossings Republik Flats Owners Association (Regd.)
            Nilabh, can you pls throw light on the status of small stretch of road near Amrapali empire, some plots are in way of road to nh 24. when is resolution expected?

            Comment


            • Re : Crossing Republik Latest Updates & Reviews

              Originally posted by nilabh9 View Post
              for any updates on township related thing please visit Crossings Republik Resident Welfare Association - CR RWA

              recently we contributed to the CROMA fund for fighting the DG issue so that it can rest in peace for always:-

              Please note:- The High Court has given judgement in favour of ownership pf land to GNN not to build DG yet.. but anyway its a long legal fight and we are on it
              And even if land belongs to GNN, GDA shows it as residential in it's masterplan

              Comment


              • Re : Crossing Republik Latest Updates & Reviews

                I am an end user, started my dream home search by RNE about a month back, didnt liked it as it was far away from my office in Noida, then luckily for me NE was cleared and I started searching there from last 10 days, went to each project there, then i saw CR adjacent to NE, I was surpurised to see the beautiful main CR socitey, We decided to book in CR but need to pay big amount upfront for CR RTM as i didnt have big savings so cant afford it now, so only option left is NE as I will pay 10 percnt and then via home loan i can afford it.
                But given a choice I prefer CR to live in, I think most of the salaried people will go to NE because of destiny and not by choice. I hope NE will also become livable like CR in 3-4 years....
                Cheers.... Ashish Sethi.

                Comment


                • Re : Crossing Republik Latest Updates & Reviews

                  Originally posted by hb_78 View Post
                  Nor in support nor against:

                  I am working in Noida and few of my friends are commuting daily from CR, and they are quite happy..... never heard anything like this from them.


                  Yaar ,

                  why telling a big lie...

                  In yahoo groups ,there is a forum called "crossing republic" ,where only CR residents are member, and you see there. Crossing residents are themselves discussing about what will happen when CR occupancy increases.

                  Man, i am not against CR ,but then just tell the truth rather than your
                  "ALL IS WELL " attitude .

                  Comment


                  • Re : Crossing Republik Latest Updates & Reviews

                    Hi,

                    Has anyone booked flat in newly launched projects Gold Coast Crossing republik, Arocon Golf or Diyansh Fabio?
                    Why these projects are hold up???
                    Any one having any idea. Please share.
                    Everytime when I am calling to these builders they are giving next date.

                    Comment


                    • Re : Crossing Republik Latest Updates & Reviews

                      Come at 8.45 a.m on Crossing main gate Gate No.1 & I would take you to Noida Sector 63 in 25 minutes on any weekdays via NH-24.while returing at 6.00 p.m I would bring u back in 15 minutes. Has someone tried..somebody told me..gandabaccha u seem to be a person who is far far from reality...