  • Re : KW Srishti Raj Nagar Extension Ghaziabad

    Hi,
    I have also booked 1040 in D block this year have visisted last sunday internal plaster is almost completed. Phase II is yet to start.
    Can anyone guide me that bathroom does not have plaster yet and still builder has sent demand letter for further payment.

    By what time is possession expected have almost paid 75% till date.

    Comment


    • Re : KW Srishti Raj Nagar Extension Ghaziabad

      Is buying flat in KW Shristi is a wise decision, I am bit afraid will they deliver their words and commitments on time? Will they are able to deliver the First Phase by Dec 2013? One more thing will phase I is available all the amenities or not if not Why they can charge maintenance from us?
      Last edited November 27 2012, 03:26 PM.

      Comment


      • Re : KW Srishti Raj Nagar Extension Ghaziabad

        Also will Phase I be liveable as Phase II is yet to be started.

        Comment


        • Re : KW Srishti Raj Nagar Extension Ghaziabad

          Originally posted by biswajit80 View Post
          Hi,
          I have also booked 1040 in D block this year have visisted last sunday internal plaster is almost completed. Phase II is yet to start.
          Can anyone guide me that bathroom does not have plaster yet and still builder has sent demand letter for further payment.

          By what time is possession expected have almost paid 75% till date.
          Builder demand payment even on 80% of work as it was the case in tower F/G. thoda aage/pichey ho sakta hai but if you will delay pym from your side then builder will not forget to charge interest pym.

          PH-II C tower next to KW office started. I had seen its raft work was going on

          Comment


          • Re : KW Srishti Raj Nagar Extension Ghaziabad

            Oh OK probably i would have missed seeing raft work in phase II.What about possession can we expect in Dec 2013

            Comment


            • Re : KW Srishti Raj Nagar Extension Ghaziabad

              Originally posted by Sunshinedel View Post
              Is buying flat in KW Shristi is a wise decision, I am bit will they deliver their words and commitments on time? Will they are able to deliver the First Phase by Dec 2013?
              its major question Dec 2013 for ph-1.Btw as major tower along with brick work is about to complete. What you think of timing for rest work.

              TOWER D/J - possible - internal plaster about to finish in dec.
              Floor laying require 4/5 month minimum march-april'13
              Then rest finishing work - not sure how much time they require
              TOWER F/G - impossible - Tower F/G brick work by Jan'13
              Internal Plaster 4/5month ie may-jun'13
              Then rest finishing work
              TOWER B/A - impossible - Tower B completed 8th floor, 2 more to go
              Tower A not started yet - So lot's work is pending

              So practically Dec'13 is not possible for Ph - 1

              Comment


              • Re : KW Srishti Raj Nagar Extension Ghaziabad

                Originally posted by biswajit80 View Post
                Oh OK probably i would have missed seeing raft work in phase II.What about possession can we expect in Dec 2013
                if possession given of PH -1 by march, 10/20% people should move there even if PH-2 work is going on. its my assumption only.

                Comment


                • Re : KW Srishti Raj Nagar Extension Ghaziabad

                  What r the current prices for Phase II as I hv low budget and can afford only where construction has started or something in resale...

                  Comment


                  • Re : KW Srishti Raj Nagar Extension Ghaziabad

                    Originally posted by Sudesh28 View Post
                    its major question Dec 2013 for ph-1.Btw as major tower along with brick work is about to complete. What you think of timing for rest work.

                    TOWER D/J - possible - internal plaster about to finish in dec.
                    Floor laying require 4/5 month minimum march-april'13
                    Then rest finishing work - not sure how much time they require
                    TOWER F/G - impossible - Tower F/G brick work by Jan'13
                    Internal Plaster 4/5month ie may-jun'13
                    Then rest finishing work
                    TOWER B/A - impossible - Tower B completed 8th floor, 2 more to go
                    Tower A not started yet - So lot's work is pending

                    So practically Dec'13 is not possible for Ph - 1

                    I feel it's still possible. Its 13 months from now. But it all depends on willingness of the builder. If he can pump good money and good manpower with good planing, than its still possible. But seeing the track record of RNE builder even I have no hope of timely completion.

                    Comment


                    • Re : KW Srishti Raj Nagar Extension Ghaziabad

                      KW AWARD - Good effort in getting 2 award per year. Best Housing Design & Best Housing Project - Same effort require to complete Ph1- by Dec'2013
                      Award means - Best project then Ajnara /Gaur/VVIP. Project yet to deliver

                      Comment