  • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

    Choor builder hai

    Dream to have a house in ggn is still a dream even after paying 85 percent n

    Big choooooor

    ch*t*ya ceo

    Originally posted by rock77 View Post
    Just checked with RP customer care and now they are saying thay Edge tower possession will start from Dec-15 onwards, GOD know when we would be able to stay in our home

    Comment


    • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

      Originally posted by mitraa View Post
      Choor builder hai

      Dream to have a house in ggn is still a dream even after paying 85 percent n

      Big choooooor

      ch*t*ya ceo
      Must see video of Mr. Nikhil Jain (Ch*t*iy* CEO):

      https://www.youtube.com/watch?v=ldzoRAMP6pY

      What an irony, he is doing completely opposite of what he said in the conference

      - labor shortage
      -timely delivery
      -customer meetings
      -customer centric

      Comment


      • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

        No ability to complete any single project

        Sent from my GT-I9190 using Indian Real Estate Forum mobile app

        Comment


        • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

          What about Atrium and View Posession

          Originally posted by rock77 View Post
          Just checked with RP customer care and now they are saying thay Edge tower possession will start from Dec-15 onwards, GOD know when we would be able to stay in our home
          Did you ask for Atrium and View possession as its almost ready and not sure why RP is not pushing that atleast.

          Comment


          • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

            Last month they said they will apply for OC in Nov. But last week they have again delayed, now they will apply for OC in Jan only.

            Comment


            • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

              Originally posted by Nilesh Dhore View Post
              Last month they said they will apply for OC in Nov. But last week they have again delayed, now they will apply for OC in Jan only.
              Hi
              Greetings

              Repeated delays, new timelines and procrastination is NOT BUSINESSLIKE behaviour.

              In a nutshell, as the towers are as good as complete, possession is pending negotiations for obtaining OC. Hope buyers will have a respite due to change of govt in state and center and probably political stake holders may mellow down a bit.

              Any idea about EWS allotment, Lifts and club??

              Cheers

              Comment


              • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

                Originally posted by BlessU View Post
                Hi
                Greetings

                Repeated delays, new timelines and procrastination is NOT BUSINESSLIKE behaviour.

                In a nutshell, as the towers are as good as complete, possession is pending negotiations for obtaining OC. Hope buyers will have a respite due to change of govt in state and center and probably political stake holders may mellow down a bit.

                Any idea about EWS allotment, Lifts and club??

                Cheers
                EWS finished. It will be allotted by govt.

                There is no club in Atrium and View.

                All lifts installed.

                Only sheer laziness and lack of competence is delaying these 2 projects.Any other company would finish in 1 month.
                Venky (Please read watch a or before posting)

                Comment


                • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

                  Originally posted by Venkytalks View Post
                  EWS finished. It will be allotted by govt.

                  There is no club in Atrium and View.

                  All lifts installed.

                  Only sheer laziness and lack of competence is delaying these 2 projects.Any other company would finish in 1 month.
                  Can they get OC without connectivity resolved?

                  Comment


                  • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

                    Originally posted by amitgup View Post
                    Can they get OC without connectivity resolved?

                    Connectivity is not an issue... 37d is well connected via pataudi n then dwarka expressway..,

                    Its just the builder who is unable to complete the project and their management needs person with real estate project management experience person not crooks like nikhil jain

                    Comment


                    • Re : Ramprastha City The Edge Towers, Sector 37D, Gurgaon

                      Originally posted by amitgup View Post
                      Can they get OC without connectivity resolved?
                      STP is main thing. Its close to completion.

                      OC is applied in advance saying basic work finished. Work need not be totally completed.
                      Venky (Please read watch a or before posting)