Folks,

I visited the site recently. Attached are some of photos from site.

- Ivory and Jemma block construction in full swing

- Amber is the next block for construction

-leveling and demarcation under progress in Amber

- company "claims" to give possession by Q2-Q3 2012.



Thanks
Attachments:
Read more
Reply
186 Replies
Sort by :Filter by :
  • Originally Posted by 2numbari
    The initial plan approved by the Town & Country department is attached for a basic understanding of the township.

    Some observations:-
    1) Revenue rastas intruding into the site plan but not bisecting - 1
    2) Revenue rastas along the boundary of the plan - 1
    3) Revenue rastas bisecting the project - 1 , the one which alienates the EWS section from the regular section.
    4) Nallahs passing through the plan -1 , again its at one far end and alienates the EWS section and taxi stand. Any reasons of worry?
    5) Unacquired patches within the plan - 2 , which have been aquired laong back.
    6) High tension wires passing through the project - None
    7) Gas/Fuel pipelines passing through the community - None
    8) Distance from the Golf Course Road Ext- 200 m onwards
    9) Sector roads (24m) being developed by the developer - All which are a part of the plan.

    The most important question:-
    How much of the above mentioned information was hidden by Emaar MGF in their numbering plan while achieving sales:- NONE , from day 1.

    Returns on investment for investors- among the highest in gurgaon* (avoiding %)

    *( Based on the knowledge that The people who have paid 18 lakhs get 55 lakhs premium and the ones who have paid 40 gets 75-80 lakhs premium
    Plots sold initially at 30 k finds buyers at 85-95k )
    {i hope somebody does not quote some random high valued purchase of 2012/ office space returns just to contest this point}


    The points which a few of my friends would want me to mention:-
    1) Delayed project
    2) No construction in two blocks yet
    3) The interest charged for delayed payment is high
    4) No clarity on the club amenities yet.
    5) Not that big a brand , not reputed , smaller FDI, poor customer services ,FEMA voilations .. really?


    The clean site plan looks more cleaner when compared with the site plan of IREO city , not very far away in terms of location. Maybe a similar evaluation of Ansal Esencia and IREO City sites and comparisons on pro rata basis would be a fair job.

    Disclaimer:- The site has grown in size over the time. Some un-acquired patches shown above have been acquired and some new may have been created. My post is based on the available data only

    Joy!


    Hi 2numbari,

    Thanks much for sharing this. Do you have the same LC for PTS project.
    Sorry for being offtopic here.
    CommentQuote
  • Any recent update on the construction progress for various blocks in Emerald hills floors....and when possession is expected
    CommentQuote
  • Emerald Hills layout

    I think that Nallah was a dry one and is no more there in the latest records. It does not show up in M3M plan as well.

    Originally Posted by 2numbari
    The initial plan approved by the Town & Country department is attached for a basic understanding of the township.

    Some observations:-
    1) Revenue rastas intruding into the site plan but not bisecting - 1
    2) Revenue rastas along the boundary of the plan - 1
    3) Revenue rastas bisecting the project - 1 , the one which alienates the EWS section from the regular section.
    4) Nallahs passing through the plan -1 , again its at one far end and alienates the EWS section and taxi stand. Any reasons of worry?
    5) Unacquired patches within the plan - 2 , which have been aquired laong back.
    6) High tension wires passing through the project - None
    7) Bundhs passing through the site - None
    8) Gas/Fuel pipelines passing through the community - None
    9) Distance from the Golf Course Road Ext- 200 m onwards
    10) Sector roads (24m) being developed by the developer - All which are a part of the plan.

    The most important question:-
    How much of the above mentioned information was hidden by Emaar MGF in their numbering plan while achieving sales:- NONE , from day 1.

    Returns on investment for investors- among the highest in gurgaon* (avoiding %)

    *( Based on the knowledge that The people who have paid 18 lakhs get 55 lakhs premium and the ones who have paid 40 gets 75-80 lakhs premium
    Plots sold initially at 30 k finds buyers at 85-95k )
    {i hope somebody does not quote some random high valued purchase of 2012/ office space returns just to contest this point}


    The points which a few of my friends would want me to mention:-
    1) Delayed project
    2) No construction in two blocks yet
    3) The interest charged for delayed payment is high
    4) No clarity on the club amenities yet.
    5) Not that big a brand , not reputed , smaller FDI, poor customer services ,FEMA voilations .. really?


    The clean site plan looks more cleaner when compared with the site plan of IREO city , not very far away in terms of location. Maybe a similar evaluation of Ansal Esencia and IREO City sites and comparisons on pro rata basis would be a fair job.

    Disclaimer:- The site has grown in size over the time. Some un-acquired patches shown above have been acquired and some new may have been created. My post is based on the available data only

    Joy!
    CommentQuote
  • Hi,

    Any Update on Work progress in Amber.

    Did anybody recieve any new payment demand.

    Cheers!!
    CommentQuote
  • Hi, is this project affected by the high court judgement today?
    Has anyone heard anything?
    CommentQuote
  • I spoke to them and have written a mail to Emaar to confirm if any impact on the project. I have a floor in Ivory block. On phone they mentioned no issue, but want them to respond in writing as well.
    CommentQuote
  • Hello friends any update on amber construction status
    CommentQuote
  • There is group created on Facebook for Emerald Hills.
    Request all to join these groups
    CommentQuote
  • EC not approved for emaar emerald hills project

    the minutes of 67th meeting of seiaa considered the project for approval for environmental clearance and was deferred as some information was not provided by emaar.

    what is the significance of this , is emaar constructing without environment approval.

    what is the judicial matter they are referring to.

    please do check with emaar as to what is this .

    ---------------

    Item No. Environment Clearance for proposed Residential Plotted Colony “Emerald Hills”, Village Badshahpur, Maidawas, Nangli Umarpur, Sector-62 & 65, Gurgaon, Haryana by M/s Emaar MGF Land Ltd.
    This case was considered in the 60th meeting of the SEIAA held on 06.11.2013 wherein it was decided to defer this case with the decision that the project proponent may be asked to submit reply to the below mentioned observations within 15 days.
    The project proponent shall submit copy of revalidated license.
    The project proponent shall submit permission of competent Authority for crossing over the Nallahs and permission for construction of culvert over the Nallah.
    The project proponent shall submit an undertaking with the declaration that
    (i) The project will have the provision for infrastructure services (water supply, sewer, storm water lines etc) to accommodate the additional load arising from population residing in other lands falling within the project limits/vicinity.
    (ii) That no construction activity shall be undertaken either on surface or below or above surface of revenue rasta passing through the project area.
    (iii) The project proponent shall indicatethe width and length of revenue rasta passing through the project area on sign board and shall display the same at both the ends of revenue rasta stretch, for awareness of public. Sign board shall also display the message that this is public rasta/road and any citizen can use it. There shall not be any gate with or without guards on revenue rasta.
    The project proponent shall submit revised water calculation @135 lpcd and water balance diagram. Sewerage and STP capacity shall also be revised accordingly.
    The project proponent shall submit revised rain water harvesting calculation @45 mm/hr.
    The project proponent shall plan, design and provide separate system of infrastructure facilities such as water supply, sewerage, storm drainage, STP and power supply etc. for different sectors of the project area.
    In the today’s meeting the reply dated 11.02.2014 was taken up for consideration in the presence of representative of the project proponent and consultant. It was observed that the project proponent has revised the lay out plan showing that revenue rasta is not intercepted due to laying of services line. The representative of the project proponent was directed to revise the water balance diagram by reducing the water requirement for horticulture use. It was noticed that the project proponent has not submitted permission of competent Authority for crossing over the nallah. The representative of the project proponent informed the Authority that the competent Authority is not granting permission for crossing over the nallah as the matter is sub-judice and is lying pending in the court. The Authority directed the representative of the project proponent to get the permission for crossing over the nallah and also submit an undertaking that no solid waste or untreated waste water will be discharged in the nallah. It was also noticed that the validity of license has already lapsed and the project proponent has submitted application for renewal of the same.
    After detailed deliberations it was decided to defer this case with the decision that the project proponent may be asked to submit reply to the below mentioned observations within 15 days or before next meeting.
    The project proponent shall submit permission of competent Authority for crossing over the nallah and an undertaking that no solid waste and untreated waste water will be discharged in the nallah. The project proponent shall submit proof of proposed approved future planning to shift the Nallahs along the road and ownership of the land covering the Nallahs.
    The project proponent shall submit copy of revalidated license.
    CommentQuote
  • Originally Posted by kinjalchato
    the minutes of 67th meeting of seiaa considered the project for approval for environmental clearance and was deferred as some information was not provided by emaar.

    what is the significance of this , is emaar constructing without environment approval.

    what is the judicial matter they are referring to.

    please do check with emaar as to what is this .

    ---------------

    Item No. Environment Clearance for proposed Residential Plotted Colony “Emerald Hills”, Village Badshahpur, Maidawas, Nangli Umarpur, Sector-62 & 65, Gurgaon, Haryana by M/s Emaar MGF Land Ltd.
    This case was considered in the 60th meeting of the SEIAA held on 06.11.2013 wherein it was decided to defer this case with the decision that the project proponent may be asked to submit reply to the below mentioned observations within 15 days.
    The project proponent shall submit copy of revalidated license.
    The project proponent shall submit permission of competent Authority for crossing over the Nallahs and permission for construction of culvert over the Nallah.
    The project proponent shall submit an undertaking with the declaration that
    (i) The project will have the provision for infrastructure services (water supply, sewer, storm water lines etc) to accommodate the additional load arising from population residing in other lands falling within the project limits/vicinity.
    (ii) That no construction activity shall be undertaken either on surface or below or above surface of revenue rasta passing through the project area.
    (iii) The project proponent shall indicatethe width and length of revenue rasta passing through the project area on sign board and shall display the same at both the ends of revenue rasta stretch, for awareness of public. Sign board shall also display the message that this is public rasta/road and any citizen can use it. There shall not be any gate with or without guards on revenue rasta.
    The project proponent shall submit revised water calculation @135 lpcd and water balance diagram. Sewerage and STP capacity shall also be revised accordingly.
    The project proponent shall submit revised rain water harvesting calculation @45 mm/hr.
    The project proponent shall plan, design and provide separate system of infrastructure facilities such as water supply, sewerage, storm drainage, STP and power supply etc. for different sectors of the project area.
    In the today’s meeting the reply dated 11.02.2014 was taken up for consideration in the presence of representative of the project proponent and consultant. It was observed that the project proponent has revised the lay out plan showing that revenue rasta is not intercepted due to laying of services line. The representative of the project proponent was directed to revise the water balance diagram by reducing the water requirement for horticulture use. It was noticed that the project proponent has not submitted permission of competent Authority for crossing over the nallah. The representative of the project proponent informed the Authority that the competent Authority is not granting permission for crossing over the nallah as the matter is sub-judice and is lying pending in the court. The Authority directed the representative of the project proponent to get the permission for crossing over the nallah and also submit an undertaking that no solid waste or untreated waste water will be discharged in the nallah. It was also noticed that the validity of license has already lapsed and the project proponent has submitted application for renewal of the same.
    After detailed deliberations it was decided to defer this case with the decision that the project proponent may be asked to submit reply to the below mentioned observations within 15 days or before next meeting.
    The project proponent shall submit permission of competent Authority for crossing over the nallah and an undertaking that no solid waste and untreated waste water will be discharged in the nallah. The project proponent shall submit proof of proposed approved future planning to shift the Nallahs along the road and ownership of the land covering the Nallahs.
    The project proponent shall submit copy of revalidated license.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.

    Routine. Usual emaar way . At times, one feels they do it deliberately to delay .
    They keep changing and making minor modifications, sometimes even redoing the old work .
    for eg sewage pipes have been relaid twice around Jemma.
    CommentQuote
  • Finally an update from Emaar for Emerald Floors - after a number of years - hope it continues. . . .attached pic
    Attachments:
    CommentQuote
  • Does anyone have any update wrt the Ivory/Jemma blocks which seem almost 100% ready.....Is there an issue in OC...? Has it even been applied for....?
    CommentQuote
  • They are waiting to get acquired. Wait and watch .

    You will get to know soon about it..

    Unitech would be next...
    CommentQuote
  • is Jemma block ready ....i was not aware 2 years back it was under litigation and even they were not digging the land also.. thastwhy i dropped the idea.
    Thanks
    CommentQuote
  • RUSHIL ARORA JI,

    Are you talking about EMAAR MGF getting acquired by some other builder ? Any idea how would this affect the ongoing projects for which they have applied for OC ?

    Thanks
    CommentQuote