  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

    There is Article in HT today about NPR, Where they mentioned that new HUDA Chief will take a stock of NPR issues this week..

    Comment


    • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

      Originally posted by Googleplus View Post
      There is Article in HT today about NPR, Where they mentioned that new HUDA Chief will take a stock of NPR issues this week..
      Chiefs will keep on changing but the situation on ground is almost same

      Comment


      • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

        God knows when this DEW issues going to be resolved.

        Comment


        • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

          I believe that the government has taken this issue quite casually and now the next date for hearing is scheduled in november 2014 to discuss again on the compensation front.Lets hope for the best !!

          P.S- Aggressive construction work by various developers on the expressway should motivate haryana govt to Clear the issues asap.

          Comment


          • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

            New Huda chief is likely to take up the matter to solution

            New Huda chief is likely to take up the matter to solution
            Lets follow the incidents coming our way in next couple of months.....

            - Haryana Assembly Elections are on 15-Oct-2014.
            - Next hearing at Hon. Punjab & Haryana High Court is on 18-Nov-2014.
            - Huda needs to speed up the file work or any other list of litigants.
            - The work on 14km out of 18 is complete....so this should be supported in the court.
            - Next steps can only be confirmed once next hearing occurs.



            Overall the things got little slow due to National Elections and Now due to Haryana Elections.

            Now we can hope the resolution of this issue after the elections....

            Lets wait & watch...
            Attached Files

            Comment


            • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

              Facts are very well clear:

              1. I surprise with statement that HA doesn't know that whether issue of pending factory owners cases are resolved, he only believe that it must have already been done. Whereas, as on date most of the factory owners are again moving to court, since they didn't get the benefits/land as directed by HC even after 4 years of verdict.

              2. HUDA has not able to acquire the land for new sectors. So, rehabilitation is impossible and on daily basis they are adding new condition and making the matter worst.

              3. Neither NHAI dispute resolved nor any progress made from Delhi side, please be remember construction being made in Delhi side not for NPR its to provide basic amenities to existing flats.

              4. Its now obvious that Haryana may have either hung assembly or another party govt, hence early resolution is distant dream. Further, it wouldn't be a priority agenda of new Govt.

              5. So far HUDA hasn't submit any policy as directed by HC despite passing nearly 4 years, hence there are fair chance that it may go against.

              Long wait easily foreseen.
              Sab 99 ka fer hain............

              Comment


              • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                Thanks for your view but what your final stand on Dew, will it get Scrap, delay more than 3 years or even more than that ...

                Sir , BTW Where do you invest as you have good insight and area you invested must be free from all litigation ?

                Comment


                • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                  Originally posted by evasnis View Post
                  Thanks for your view but what your final stand on Dew, will it get Scrap, delay more than 3 years or even more than that ...

                  Sir , BTW Where do you invest as you have good insight and area you invested must be free from all litigation ?

                  DEW will be completed in 2015
                  Nothing Surprises Me

                  Comment


                  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                    Originally posted by VB_States View Post
                    DEW will be completed in 2015
                    Great for DEW, but how did u conclude that DEW would be completed in 2015, any specific documents to back this claim or u r just looking at circumstantial evidence ?

                    Download our Android App! | Please Read IREF Rules | FAQ's

                    Comment


                    • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                      I don't think DEW will be functional by 2015 even if they start work by now.