A lot of companies are advertising for property citing nearness to Dwarka expressway corridor.

Shilas, Indiabulls Centrum Park and Ramprastha Edge Tower come to mind.

Does anybody have news on when this construction will start and when it is likely to finish? Has the contract been awarded and to whom?
Date of completion and start of operation will be vital news for evaluating the pricing of flats sold in this corridor.

Last I heard was that a few houses in Palam Vihar were slated for demolition for this expressway in May June 09 or thereabouts.
Read more
Reply
19802 Replies
Sort by :Filter by :
  • Originally Posted by Bala2107
    Has padmini VNA premises fully cleared and levelled. Its important that piece of road gets laid by the time the ROB gets completed, else the ROB is of little use.
    Also while this is a big boost to the commuting capabilities of many sector around that area, the real breakthrough for DWAY is NPV, KD & Delhi. So I am basically interested in the real on-ground movements of these three areas, because the ROB and small encroachments etc, are not big issues, its the matters that are sub-judice that's a big pain. WE all know how much harm litigation matters can cause to projects, public or private. With no fastracking or clubbing of common issues (project wide clubbing) or other judicially sanctioned monitoring process of land issues in national interest, there is little hope of matters getting quick clearances. While Supreme court and High courts are busy hearing political cases, where is the time for national interest?

    I really hope that the conclusive push to NPV and KD has now come and PHHC deliers a quick verdict on the GPA/SPA cases and appoints an observer under whom HUDA will have to settle the matter within a defined time frame of 4-5 weeks and handover the project lands to NHAI.

    So in the next 3-4 months, if we can get a clear direction & KD/NPV land possession, NHAI delhi land acquisition process pick ups steam with on ground possessions, and the metro Dwarka - IFFCO chowk route gets announced with DMRC's consent. Only then it makes sense to start following this area once again. Becuase that means that DEWAY can be fully motorable in 15-18 months. Although work will keep happening (ROB, FOB, Service Roads, widening, Horticulture, clover leaf junctions etc. etc.) for the next 5-7 years, things will be clear and people will start moving in after 15 months into their projects.


    Its been months since the Padmini Factory has been demolished. There is a motorable road now which is waiting to be black topped.
    CommentQuote
  • Drain being made alongside the road where Padmini factory used to be there earlier. Work is being done in a synchronised manner, so that drains are complete just before the black topping of the ROB & road stretch in front of it.

    Waterline already laid. Its visible in the lower right hand corner. Its coming from Chandu water treatment plant.

    Walkways/cycleways have been provided on the side of the ROB
    Photos:
    CommentQuote
    2 Comments
    • Bala210710 months ago
      Thanks @highway, I havent been that side in a couple of months atleast. The last time I went to Dway I just visited my project at 111 and came back. good to know Padmini factory place which was being demolished earlier is now a road !
  • Any update on new ROB work at Bajghera Crossing. It was closed for 2 years, with aim to provide connectivity across railway line.
    CommentQuote
  • Originally Posted by highway
    Drain being made alongside the road where Padmini factory used to be there earlier. Work is being done in a synchronised manner, so that drains are complete just before the black topping of the ROB & road stretch in front of it.

    Waterline already laid. Its visible in the lower right hand corner. Its coming from Chandu water treatment plant.

    Walkways/cycleways have been provided on the side of the ROB


    Yes, more or less this is what it looked like.Missed seeing the drain though.
    CommentQuote
  • CommentQuote
  • Originally Posted by Khalsa
    Yes Delhi door nahin and Basanti will get married.


    Does anybody still have doubt that it is still not too early for Basanti to get married; please share counter views.
    CommentQuote
    2 Comments
    • samggn10 months ago
      Wonder why Hindustan Times is publishing incomplete & misleading information...work not only continued, but the main cementing work of all the spans on both the sides already complete.
      The plan is for the ROB to be made 12 lane later on. Existing ROB is being completed at full speed, to make it operational by this month end.
  • Originally Posted by Tiger1


    Does anybody still have doubt that it is still not too early for Basanti to get married; please share counter views.


    People will always continue to doubt unless they have gone and seen what is actually happening, since its contrary to what had been happening over the past few years.
    Some people have posted photos as well of the actual work, but people continue to doubt that as well.
    CommentQuote
  • Latest Update on Dwarka Expressway:

    1. For Kherki Daula oustees physical possession is being given today in 37C.

    2. Yesterday HUDA carried out another demolition drive in Sec 110A.

    3. HUDA demolished the remaining unauthorized structures in 110A. Mixture plant is being removed.

    4. Plot demarcation of sec 110A is being done to finalise the plot block for possession, after demolition of remaining structures.

    5. Physical possession to oustees in 110A should happen by next week.
    CommentQuote

  • Demolition in 110a to get the plots ready. Will be handed over next week.
    Ulti time for eye test and counting test again
    Attachments:
    CommentQuote
  • Thank you Mr Highway and Mr Sharad for your updates:D
    CommentQuote
  • Originally Posted by highway
    Latest Update on Dwarka Expressway:

    1. For Kherki Daula oustees physical possession is being given today in 37C.

    2. Yesterday HUDA carried out another demolition drive in Sec 110A.

    3. HUDA demolished the remaining unauthorized structures in 110A. Mixture plant is being removed.

    4. Plot demarcation of sec 110A is being done to finalise the plot block for possession, after demolition of remaining structures.

    5. Physical possession to oustees in 110A should happen by next week.


    HUDA is acting fast and clearing all obstacles one by one.
    CommentQuote
  • Where is Ulti Ji these days?.
    CommentQuote
    2 Comments
    • pointer10 months ago
      Nexus hai Babu Bhaiya.. Nexus hai!
  • Gurgaon NPR project hurdle: Huda gives allotment letters to 60 oustees

    Clearing a major hurdle to the completion of Dwarka Expressway, the Haryana Urban Development Authority (Huda) on Wednesday gave possession letters to about 60 people who were evicted to make way for the Northern Peripheral Road (NPR) project.

    Read more at:
    http://m.hindustantimes.com/gurgaon/...0xMWc897M.html
    CommentQuote
  • Originally Posted by rohit_warren


    No matter how hard you try which you are doing for last 5 years - d eway is doomed and people are stuck for looooooong time - for last two years no one wants to even look at that place - all annoucements which happened during every july aug every year was just a drama by the builder bankers babus and brokers - agar meri baat maini hoti to apne ghar mai hote arur money double ho gayi hoti -

    Jo bola wo ho kar rahega - its plain simple science not a rocket science - waise bhi gurgram has started to going back to its gaon status - I know 10 big companies who have moved out of gurugram to bangalore - 10 big companies means 20k jobs - gurgaon errrr guruGRAM all set to become the village it was once .
    there are so many examples all over the world where a region boomed and doomed when it was just dependent on one sector of economy take some cue - act smart get back to somewhere where the economic activities are not limited to one sector


    Originally Posted by rohit_warren
    Seems that I will get an affordable housing unit in D Eway very soon.

    Good once again my patience is going to reward me - I saw a tell tale sign of some price corrected project on D Eway sec 92.

    Coming 3 months would be interesting
    Rohit

    https://www.indianrealestateforum.com/forum/city-forums/ncr-real-estate/gurgaon-real-estate/13876-real-estate-bubble-set-to-burst-again-in-india?p=306090#post306090


    Was reading old posts and came across something which caught my eye after a few pages. It seems you wanted to buy in Sect 92 many years ago. What happened to it? Despite the present scenario, prices are double in that area for the delivered projects.
    CommentQuote
  • Originally Posted by highway
    Gurgaon NPR project hurdle: Huda gives allotment letters to 60 oustees

    Clearing a major hurdle to the completion of Dwarka Expressway, the Haryana Urban Development Authority (Huda) on Wednesday gave possession letters to about 60 people who were evicted to make way for the Northern Peripheral Road (NPR) project.

    Read more at:
    http://m.hindustantimes.com/gurgaon/...0xMWc897M.html


    I had rec'd news about this, and also was told about the New Palam Vihar area being tackled soon. Seen the pictures, but isn't there more work needed in this place.