  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

    This is reply to an RTI filed on October 13, 2016.

    Click image for larger version

Name:	RTI - Notification of NPR as a National Highway.jpg
Views:	1
Size:	50.4 KB
ID:	2492747

    Comment


    • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

      The entire focus seems to be shifted to New Gurugram again. Hot topics being discussed:
      1. DEW taking up some shape
      2. Global city project
      3. New metro route
      4. Jaipur super expressway
      5. Toll shifting ahead
      6. Hero honda flyover

      If all this becomes reality, this is going to be a very good area to stay, till then, we anyways have this forum

      Comment


      • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

        Taaja Khabar
        Click image for larger version

Name:	IMG-20170325-WA0002.jpg
Views:	2
Size:	81.0 KB
ID:	2492778
        Click image for larger version

Name:	IMG-20170325-WA0002.jpg
Views:	2
Size:	81.0 KB
ID:	2492779

        Comment


        • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

          Originally posted by palmahla View Post
          Taaja Khabar [ATTACH=CONFIG]n2492778[/ATTACH] [ATTACH=CONFIG]n2492779[/ATTACH]
          This is the last hurdle of NPR, may things come under the favour of genuine home buyers

          Comment


          • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

            Hi can anyone plz throw some light on chintels paradiso vs ats kocoon vs experion heartsong?

            What are the major pros n cons of these projects?

            ​​​​​​u may make necessary assumptions.

            Comment


            • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

              Originally posted by Choma1 View Post

              This patch was constructed about a year ago in March 2016. This patch does not have a road on either end. The road has been constructed with a width of about 42 to 45 meters. It is 21 to 22. 5 meters on each side from the center of the NPR. However, center point of NPR, on this stretch is out by about 18 meters. Therefore, NPR is taking a curve here which is not there in the Zonal Plan. This issue had been taken up with the administrator and the executive engineer. The executive engineer wondered how there can be a curve in the road. He was clearly not aware of the curve. The administrator admits, in private, that it is a violation of the Zonal Plan but he will not do anything to correct the alignment as per the Zonal Plan. The administrator has clearly expressed his inability to correct the alignment. If one talks about the sincerity of HUDA, this is how serious HUDA is. The matter was then taken up with Rao Nirbir, PWD minister and also the MLA from New Palam Vihar. He has referred the matter officially to HUDA. The same has been referred to NHAI now. NHAI is currently looking into this issue. However, this matter ,very likely, will end up in the High Court within a fortnight. Watch out for this case as it will have major repercussions on the construction of NPR. Why and for what consideration the approved alignment has been changed on the ground is anybody's guess? However, once this matter ends in the High Court, it is very likely that a stay will be granted on the construction of NPR in this stretch as it is being built in violation of the Zonal Plan. The implication of the changed alignment will be that NPR, once completed, will have to be pass through the private unacquired lands and houses. No Court, worth its name, will allow this kind of violation of the Master Plan.
              I think that as the matter was brought to the notice of HUDA and NHAI, HUDA has removed the pillars that it had put previously indicating the alignment of the road, based on the changed alignment. Now, the pillars have been put as per the correct alignment i.e. alignment based on the land acquired. Even though the changed alignment currently is within the 150 meters of the acquired land, however, the alignment within those 150 meters is out by about 18 meters. Therefore, once the project land is taken over by NHAI, any construction already done by HUDA on either side of the road like sewer lines, water lines etc. will have to be removed as without removing that civil construction work, the alignment cannot be straightened.

              Comment


              • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                Originally posted by Choma1 View Post

                I think that as the matter was brought to the notice of HUDA and NHAI, HUDA has removed the pillars that it had put previously indicating the alignment of the road, based on the changed alignment. Now, the pillars have been put as per the correct alignment i.e. alignment based on the land acquired. Even though the changed alignment currently is within the 150 meters of the acquired land, however, the alignment within those 150 meters is out by about 18 meters. Therefore, once the project land is taken over by NHAI, any construction already done by HUDA on either side of the road like sewer lines, water lines etc. will have to be removed as without removing that civil construction work, the alignment cannot be straightened.
                You haven't taken the green belt and service road into account. Even 18m out of alignment for the time being is not a problem within the whole stretch.

                Comment


                • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                  Originally posted by hsgulati View Post
                  The entire focus seems to be shifted to New Gurugram again. Hot topics being discussed:
                  1. DEW taking up some shape
                  2. Global city project
                  3. New metro route
                  4. Jaipur super expressway
                  5. Toll shifting ahead
                  6. Hero honda flyover

                  If all this becomes reality, this is going to be a very good area to stay, till then, we anyways have this forum
                  1 & 6 are no longer an "if", and will be complete soon. Leave the flyovers on the DEW out for the time being.
                  5 will take a bit longer, unless all parties agree to pay the compensation to the toll operator.
                  3 will be happening soon as well
                  2 & 4 are the only items that will take a few years more.

                  Comment


                  • pointer
                    pointer commented
                    Editing a comment
                    "3 will be happening soon as well"
                    is this based on some confirmed info or just a hope

                • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                  Hearing is on 29 March 2017 however at the end of previous order the date mentioned was 28 March 2017

                  Case Link : https://phhc.gov.in/enq_caseno.php?v...2260&var3=2008

                  Comment


                  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                    Hearing is on 28 March 2017.

                    https://phhc.gov.in/enq_caseno.php?v...2594&var3=2016

                    Comment


                    • guruDCR
                      guruDCR commented
                      Editing a comment
                      any result of todays hearing highway bhai

                    • highway
                      highway commented
                      Editing a comment
                      Next hearing on 5 April 2017