NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

Last updated: 1 hour ago
21738 | Posts
  • Time
  • Show
Clear All
new posts

  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

    Originally posted by Bikumatre View Post
    Proceedings of the Review Meeting of Gurgaon Zone held under
    the Chairmanship of Sh. S.S.Dhillon, IAS, Financial Commissioner
    and Principal Secretary, Town & Country Planning Deptt. Haryana
    on 24.12.2011 at 11:00 A.M. at Gymkhana Club, Sector-29,
    Gurgaon.


    8.
    Northern Periphery Road.

    Chief Engineer stated that 800 mtr. portion of road is to be constructed in Delhi area and there is no provision to construct road in Delhi area as per scheme of Delhi Govt. However, the matter was clarified by FCTCPHaryana that there is already provision of the said road in the K-2 Zonal place
    of Delhi Govt. hence this was not a problem. FCTCP discussed the matter in detail with Chief Engineer regarding construction of intersections and
    underpass and expressed need/ requirement of construction of Flyovers at a distance of 2-3 KM i.e at Bujhghera, Daultabad, Pataudi and Farrukh Nagar.

    Chief Engineer was asked to engage some consultant for consultancy of ROB.Mr.Vij, Member (Retd.) from Railway Board who has executed plan of
    construction of ROBs within 9 months
    may be consulted for the construction of ROBs immediately to make the said road functional.
    FCTCP decided that because village roads are substituted with sector roads so village roads are not be retained as these to be merged at
    intersection-underpass on main sector roads cross and expenditure should not be made where flyovers are to be constructed till the finalization of the ROBs. XEN Hort. to plan the plantation plan in 1
    st phase on footpath of 7 meter stretch along NPR. Good varieties of Neem, Fycus and Tilkhan etc. trees can be planted. Structures falling in the alignment of NPR, award of which have been announced, may be auctioned by the Estate Officer-I in a time bound manner.


    This is a very good news that they have taken note of the ROB issue so that in the coming 12-18 months , the non litigated patch can be made functional

    Comment


    • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

      Originally posted by amit.bhalla View Post
      This is a very good news that they have taken note of the ROB issue so that in the coming 12-18 months , the non litigated patch can be made functional
      Hi
      Greetings

      I am thinking that by mention of Mr VIJ, duration refers to only THE PLAN for construction as I am 100% sure this does not mention ACTUAL CONSTRUCTION of the ROB.

      I wish it would be ACTUAL CONSTRUCTION in 9 months but I could bet any amount if this could be possible with HUDA and Railways JV

      Devil in detail..

      Cheers

      Comment


      • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

        On the 18-km Northern Peripheral Road, there are 15 problem areas

        HT Correspondent, Hindustan Times
        Gurgaon, May 07, 2012
        The Haryana Urban Development (Huda) has finally woken up to the cost overruns caused due to mounting delays in big-ticket road projects NPR and SPR expressways. Besides, there has been pressure from Chandigarh to find a solution to outstanding issues as cost escalation is burning a hole in the governments pockets.
        In a meeting held last week, the Huda authorities identified 15 problem areas on the NPR project, which could be resolved easily as in some of these disputes involve other state government departments.
        These problems can be resolved at a different plane as they do not involve compensation issues.
        There are 15 bottleneck areas on the 18-km stretch of the NPR. I have asked all concerned officials to submit an action taken report at the earliest, said Huda administrator Praveen Kumar.
        The issues are small but need to be dealt with seriously, he added.
        According to the administrator, the Huda estate office has to remove as many as four constructions coming up on the way of NPR at four locations, while the land acquisition department has to work to vacate stays in as many as four cases and acquire land at two locations.
        The NPR connects Dwarka in Delhi to Kherki Daula in Gurgaon. The project is expected to be completed by October, 2012.
        The department like Haryana Vidyut Prasaran Nigam (HVPN) has to remove electric poles, the Haryana State Industrial and Infrastructure Corporation (HSIIDC) too has to remove one structure at Udyog Vihar Phase-5.
        The administrator has directed his officials to submit a detailed action taken report latest by May 15.
        The NPR project was awarded to India Bulls, a private developer.
        The deadline for the project is March 31, 2012 which is unlikely to be met, given the current pace of work.
        Only 12.5km of the road is free of litigation.
        The uncertainty over the NPR project is also hitting the real estate sector very hard.
        However, many private developers have already launched their projects along the under-construction expressway.

        Comment


        • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

          They were touted as the lifeline of the Millennium City and a panacea for its perennial traffic woes. But a slew of litigations and other issues have held up the ambitious projects 18-km-long northern peripheral road (NPR) and southern peripheral road (SPR). The NPR, which is also known





          as Dwarka expressway, is mired in land cases. Of the 18 km, only 12.5 km is free of any litigation.
          Nearly 750 families are up in arms against Haryana government over land compensation.
          The cases are heard in Punjab and Haryana High Court. The project started in 2008.
          The families are demanding alternative plots at Sector 110-A, which is a planned and developed Haryana Urban Development Authority (Huda) sector close to Dwarka. The government is not agreeing to allot us plots at developed Huda sectors. The matter has been pending in the high court since 2008, said Rishi Raj Rana, who heads a group of affected people who have approached the high court.
          However, Huda chief administrator DPS Nagal has denied the allegations.
          Their demands have been continuously increasing. They don't stick to one demand or one convincing formula so that the matter could be solved amicably. They are not satisfied with 50 square yard plots. They need bigger plots and more than one for each family. This is not possible, said the chief administrator.
          The court case has stalled the work on NPR.
          The government should appoint a committee to solve the issue and speed up NPR progress work. At the same time, the high court can appoint an amicus curie for early disposal of the cases," said Navin Raheja, president of the National Realty Development Council (NRDC).
          The NPR connects Dwarka in Delhi to Kherki Daula in Gurgaon. The project was to be completed by March this year, but a revised deadline has been set for October, 2012.
          Similarly, the work on SPR was held up because of another litigation. The R400 crore project, divided into two segments, connects Kherki Daula on NH-8 to Ghata village near Sector 55, further to Faridabad-Gurgaon Road.
          The government on its part has shown utter negligence in solving the issue of Darbaripur, a small village, which is coming in the way of the expressway between Sohna Road and NH-8.
          These villagers have also approached the high court and accused the government of forcibly acquiring their forefathers' land and displacing them for the benefit of the developers.
          The project was allotted in June, 2010 for completion in December, 2010. SPR's extended deadline is now December, 2012.
          We are not going to leave our ancestral land. We have been here for hundreds of years and the government did not even think of informing us that they are planning to acquire the land," said Rambir Singh, a resident of the village.
          He alleged that the government has conspired with the developers to snatch their land.
          "We are not going to compromise at all with this land," he added.
          When asked what were his comments on such vehement arguments, the chief administrator said the two mega projects were the future growth of the Millennium City and these "small and minor issues" can be settled.


          ------------------------------------------------------------------------------------

          Ambitious projects at crossroads - Hindustan Times

          Comment


          • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

            sublimation & Bikumatre, thanks for the share .

            Originally posted by Bikumatre View Post
            They were touted as the lifeline of the Millennium City and a panacea for its perennial traffic woes. But a slew of litigations and other issues have held up the ambitious projects 18-km-long northern peripheral road (NPR) and southern peripheral road (SPR). The NPR, which is also known as Dwarka expressway, is mired in land cases. Of the 18 km, only 12.5 km is free of any litigation.

            Nearly 750 families are up in arms against Haryana government over land compensation.

            The cases are heard in Punjab and Haryana High Court. The project started in 2008.

            The families are demanding alternative plots at Sector 110-A, which is a planned and developed Haryana Urban Development Authority (Huda) sector close to Dwarka. The government is not agreeing to allot us plots at developed Huda sectors. The matter has been pending in the high court since 2008, said Rishi Raj Rana, who heads a group of affected people who have approached the high court.

            However, Huda chief administrator DPS Nagal has denied the allegations.
            Their demands have been continuously increasing. They don't stick to one demand or one convincing formula so that the matter could be solved amicably. They are not satisfied with 50 square yard plots. They need bigger plots and more than one for each family. This is not possible, said the chief administrator.

            The court case has stalled the work on NPR.

            The government should appoint a committee to solve the issue and speed up NPR progress work. At the same time, the high court can appoint an amicus curie for early disposal of the cases," said Navin Raheja, president of the National Realty Development Council (NRDC).

            The NPR connects Dwarka in Delhi to Kherki Daula in Gurgaon. The project was to be completed by March this year, but a revised deadline has been set for October, 2012.

            Similarly, the work on SPR was held up because of another litigation. The R400 crore project, divided into two segments, connects Kherki Daula on NH-8 to Ghata village near Sector 55, further to Faridabad-Gurgaon Road.

            The government on its part has shown utter negligence in solving the issue of Darbaripur, a small village, which is coming in the way of the expressway between Sohna Road and NH-8.

            These villagers have also approached the high court and accused the government of forcibly acquiring their forefathers' land and displacing them for the benefit of the developers.

            The project was allotted in June, 2010 for completion in December, 2010. SPR's extended deadline is now December, 2012.

            We are not going to leave our ancestral land. We have been here for hundreds of years and the government did not even think of informing us that they are planning to acquire the land," said Rambir Singh, a resident of the village.

            He alleged that the government has conspired with the developers to snatch their land.

            "We are not going to compromise at all with this land," he added.

            When asked what were his comments on such vehement arguments, the chief administrator said the two mega projects were the future growth of the Millennium City and these "small and minor issues" can be settled.


            ------------------------------------------------------------------------------------

            Ambitious projects at crossroads - Hindustan Times
            Download our Android App! | Please Read IREF Rules | FAQ's

            Comment


            • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

              Govt has a positive approach to end outstanding issues... but cant accept land owners all demands l

              Hindustan Times
              Gurgaon, May 07, 201First Published: 01:00 IST(7/5/2012)

              SS Dhillon, Financial commissioner-cum-principal secretary, town and country planning department, Government of Haryana on land issues in the state.

              Has the government made any serious effort to solve the land compensation issue?

              Yes, the Haryana government has adopted a positive approach to solve this issue time and again in the court. The government will look into all possible aspects to solve the problem at the earliest.

              Is the government going to adopt a holistic approach in the court?

              We are working in this regard. We have sought a detailed report from the Gurgaon administrator. We will approach the court for early disposal of the cases.


              There have been allegations that the government has connived with the developer for mutual benefits. Isthere any truth in this?

              There is no truth at all in such allegations. The government never acts that ways. In this case, the government examined all the possibilities and then opted for the route affecting the minimum number of people. Now, many people have joined the march against the government in lust of compensation.

              What is the government's stance now? Is it ready to meet the demand of affected people?

              The government has already offered alternative plots to the affected families. But unfortunately, this has not materialised. The government is still serious about its offer. But we will not meet the villagers fluctuating demand at all.

              Comment


              • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                Originally posted by TAggarwal View Post
                Hindustan Times
                Gurgaon, May 07, 201First Published: 01:00 IST(7/5/2012)
                What is the government's stance now? Is it ready to meet the demand of affected people?

                The government has already offered alternative plots to the affected families. But unfortunately, this has not materialised. The government is still serious about its offer. But we will not meet the villagers’ fluctuating demand at all.
                Hi
                Greetings

                Its hard to comprehend how will a person move in a smaller sized plot as recommended by the R&R policy?? How can the govt logically find a solution to the greed and lust of compensation as mentioned above news articles??

                Moreover, all plots are not fully authorised and therefore those who have illegal and unauthorised occupation cannot be legally compensated.

                15 issues mentioned by the Administrator are purely on the matters of...
                -litigations,
                -clearance of obstructions,
                -movement of High tension pylons and
                -acquiring land with other Haryana govt authorities/departments.

                There is no mention of time, status, survey, approval etc about more serious issues like ROB, Under passes, Toll issue, Delhi connectivity.

                Govt appears to be embroiled more with issues within the realm of Haryana govt and very likely will give a curt revert on issues concerning center, court, MCD and Delhi Govt.

                Now govt is giving signals of cost overruns.. therefore it is 100% likely that EDC will be increased due to time and cost overruns.

                Same problems, same govt, same administration, same outcome..

                Albert Einstein Quotes
                Insanity: doing the same thing over and over again and expecting different results.


                Cheers
                Last edited by BlessU; May 7 2012, 12:16 PM.

                Comment


                • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                  Ray of BIG hope ...

                  Again Northern Peripheral Road is in news with the concern form Chandigarh and HUDA regarding the delays. Indeed its good news because the officers from Haryana government are now busy in reviewing the cause of administrative and construction related delays and also reminding Delhi government about integration of NPR with already planned master plan road of Delhi Master Plan 2021.

                  I believe, still more seriousness and priority is required on structural part (ROBs, Interchanges and Flyovers) and solving the issues related to litigation stretches.

                  At least now the picture is very much clear regarding the inter-departmental (HUDA-HSIIDC-HVPN) conflicts that can be solved by better coordination. Its a well known matter of bad practices amongst all government departmetns that hey always lacks coordiantion and team work ultimately resulting into the wastage of public money.

                  Waiting for atleast 12.50 kms of litigation free stretch to be completed till October 2012 with NH-8 connectivity and without ROB over Delhi-Jaipur Railway Line....... (To be honest it is justified based on current progress of work-
                  __________________________________________________ __________
                  It is better to be blind than to see things from only one point of view

                  Comment


                  • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                    फिफ्थ ईयर प्लान बन गया एनपीआर!

                    फिफ्थ ईयर प्लान बन गया एनपीआर!


                    एनबीटी न्यूज ॥ गुड़गांव

                    दिल्ली के द्वारका से गुड़गांव के खेड़कीदौला को जोड़ने के लिए बनाए जा रहे नॉर्दर्न पेरिफेरल रोड ( एनपीआर ) का काम अटक गया है। इसके बनने के बाद द्वारका से जयपुर जाने वाली गाडि़यों को शहर के अंदर नहीं आना पड़ेगा। इस 90 मीटर चौड़ी रोड का सपना दिखाकर कई बिल्डर्स ने 100 से ज्यादा हाउसिंग स्कीम लॉन्च कर दीं। इसके किनारे 5 एसईजेड प्रस्तावित हैं। लेकिन रोड बनाने का काम आगे नहीं बढ़ पा रहा है। 18 किमी की रोड बननी है जिसमें से अभी तक 14 किमी का ही टेंडर जारी किया जा सका है। इस पर भी 30 से 35 फीसदी ही काम हुआ है। पहले इसे 31 मार्च , 2012 तक टारगेट पूरा करना था , अब समयसीमा अक्टूबर , 2012 कर दी गई है। वहीं , जानकारों का कहना है कि वास्तविक हालात को देखने से लगता है कि कम से कम इसे पूरा होने में 3 साल लग जाएंगे। अभी तक फ्लाईओवर का डिजाइन ही तैयार नहीं हो सका है। हाइटेंशन लाइन को भी शिफ्ट करने की कार्रवाई शुरू नहीं हो सकी है। 4 किमी के हिस्से पर हाई कोर्ट का स्टे है।


                    एनपीआर का ठेका 1 अप्रैल , 2011 को 132 करोड़ में छोड़ा गया था। इसकी कुल लंबाई 18 किलोमीटर है। इसमें 4 किलोमीटर एरिया पर अदालत का स्टे है। पिछले साल हूडा ने 14 किलोमीटर सड़क निर्माण का टेंडर करीब 44 करोड़ रुपये में एक कंपनी को सौंपा था। इसकी डेडलाइन 31 मार्च निर्धारित की गई थी। अब तक इसमें से करीब 30 से 35 प्रतिशत काम ही कंप्लीट हो सका है। यह रोड दिल्ली के द्वारका से शुरू होगा जो एनएच 8 से खेड़कीदौला गांव में जाकर मिलेगा। इसके निर्माण के बाद गुड़गांव शहर के अंदरूनी हिस्से में ट्रैफिक कम हो जाएगा। द्वारका से मानेसर की तरफ जाने वाले वाहन इस रोड से सीधा निकल जाएंगे। इस रोड पर कई सेक्टर बने हैं। इनमें 100 से ज्यादा हाउसिंग स्कीम लॉन्च की गई है। इसके अलावा 5 एसईजेड भी हैं। यह एक अति महत्वपूर्ण प्रोजेक्ट है। इसे द्वारका एक्सप्रेस के नाम से भी जाना जाता है।


                    क्या हैं अड़चनें

                    इस एरिया में 9 फैक्ट्री आ रही हैं , जो बजघेड़ा , बसई व खेड़कीदौला गांव में हैं। पंजाब एंड हरियाणा हाई कोर्ट ने इस जमीन के बदले में फैक्ट्रियों को अलटरनेट प्लॉट देने के आदेश दिए हैं। इस मामले में अभी तक हूडा ने कोई कारगर कार्रवाई नहीं की है। इस वजह से अभी तक फैक्ट्री मालिकों को जमीन नहीं मिल सकी है। जमीन मिलने के 9 महीने के अंदर उस पर फैक्ट्री का निर्माण करना है। एक्सपर्ट की राय है कि इसमें एक साल तो लगेगा ही।


                    एनपीआर के रास्ते में पटौदी रोड , फर्रुखनगर रोड , बजघेड़ा रोड व दौलताबाद रोड पर फ्लाईओवर का निर्माण किया जाना है। अब तक इसका डिजाइन ही तैयार नहीं हो सका है। डिजाइन तैयार होने के बाद उसे मंजूर करवाया जाएगा फिर एस्टिमेट बनेगा। इसके बाद एस्टिमेट मंजूर होगा। टेंडर आमंत्रित करने और उसे अलॉट करने की प्रक्रिया में भी कम से कम 2 साल लगने की बात कही जा रही है।

                    एनपीआर के रास्ते में एचवीपीएन के 66 केवीए के 6 टावर भी आ रहे हैं। टावर और लाइन को शिफ्ट करने में भी कम से कम एक से डेढ़ साल तक का समय लगेगा।

                    रोड का 500 मीटर का टुकड़ा जमीन नहीं मिलने के कारण अटका है। यह लैंड एक निजी कंपनी की है। इसे दिलवाने का आग्रह एचएसआईआईडीसी के अधिकारियों से किया गया है।

                    4 किलोमीटर रास्ता का अभी टेंडर अलॉट नहीं किया गया है। यह जमीन अदालती पचड़े में फंसी है। न्यू पालम विहार में करीब 250 मकान व खेड़कीदौला के करीब 150 मकान एनपीआर के रास्ते में आ रहे हैं। पिछले साल पंजाब एंड हरियाणा हाई कोर्ट ने हूडा व याचिकाकर्ताओं को एकसाथ बैठकर मामला सुलझाने के आदेश दिए थे। अभी तक यह विवाद सुलझ नहीं सका है। लोग प्लॉट के बदले में प्लॉट व कंस्ट्रक्शन कॉस्ट का मुआवजा चाहते हैं। हूडा पॉलिसी के अनुसार प्लॉट दे सकता है। इसके चलते यह मामला बीच में ही अटका हुआ है।


                    कोट

                    एनपीआर की राह क्लियर करने के लिए 2 दिन पहले ही एक बैठक ली गई थी। इसमें हूडा के अलावा एचवीपीएन , भूमि अधिग्रहण ऑफिस , टाउन एंड कंट्री प्लानिंग डिपार्टमेंट व एचएसआईआईडीसी के अधिकारियों ने हिस्सा लिया था। सभी को निर्देश दिए गए हैं कि एनपीआर का निर्माण जल्द से जल्द करवाने का प्रयास करें। अड़चनों को देखने से लगता है कि अभी इसके निर्माण में समय लगेगा।

                    - डॉ . प्रवीण कुमार , ऐडमिनिस्ट्रेटर हूडा




                    फिफ्थ ईयर प्लान बन गया एनपीआर! - Navbharat Times
                    Download our Android App! | Please Read IREF Rules | FAQ's

                    Comment


                    • Re : NPR - Northern Peripheral Road, Dwarka Expressway, Gurgaon Updates

                      Originally posted by MANOJa View Post
                      फिफ्थ ईयर प्लान बन गया एनपीआर!




                      एनबीटी न्यूज ॥ गुड़गांव

                      .......

                      Quote...

                      "एनपीआर की राह क्लियर करने के लिए 2 दिन पहले ही एक बैठक ली गई थी। इसमें हूडा के अलावा एचवीपीएन , भूमि अधिग्रहण ऑफिस , टाउन एंड कंट्री प्लानिंग डिपार्टमेंट व एचएसआईआईडीसी के अधिकारियों ने हिस्सा लिया था। सभी को निर्देश दिए गए हैं कि एनपीआर का निर्माण जल्द से जल्द करवाने का प्रयास करें। अड़चनों को देखने से लगता है कि अभी इसके निर्माण में समय लगेगा। "

                      - डॉ . प्रवीण कुमार , ऐडमिनिस्ट्रेटर हूडा


                      फिफ्थ ईयर प्लान बन गया एनपीआर! - Navbharat Times
                      Quote को देखकर तो ऐसा लगता है Project completion की नई तारीख देने के लिए मीटिंग की थी अपने परवीन भाई फरीदाबाद वाले ने
                      __________________________________________________ __________
                      It is better to be blind than to see things from only one point of view

                      Comment