Our site is in kondhwa budruk.19 floorey bldg.bldg is near about complete. Our builder say file is stuck in defence NOC for final completion certificate.Does Bldg require defence NOC . its mor than 17-18 km from airport/NDA.and plan sanctioned before 2016
Read more
Reply
1 Replies
Sort by :Filter by :
  • Please check project details on RERA website and raise a complaint with RERA if builder is past the project completion date mentioned on RERA website
    CommentQuote